Construction of a twin track viaduct for the Jurong Line
VSL Singapore has been appointed by McConnell Dowell/John Holland JV as their specialist sub-contractor for the following scope of work for the Jurong Region Line Contract J108:
- the erection of precast segments using 2 units Launching Gantries for both span by span method (1,013 segments) and balanced cantilever method (396 segments) and 4 units of lifting frames;
- Post-tensioning work (more than 1000ton)
Onsite works, which will involve 100 people at peak periods, started on site at the end of 2021 and will last for 18 months.